What is Long lead time items?
Long lead time items are SKUs that take a long time to arrive after you order them, usually because the supplier is overseas or manufactures to order rather than holding stock.
Long lead time items need more planning buffer than everything else in your store. If you order them the same way you order fast local stock, you will run out while waiting weeks or months for the new batch to arrive.
The fix is to calculate the order-by date for these items using their real lead time and current sales pace, then place the order well before stock gets low. Reviewing these SKUs separately, on their own schedule, keeps them from getting lost among items that reorder weekly.
Formula
Example
A candle store sources glass jars from an overseas supplier with a 70 day lead time. The store sells 10 jars a day and has 900 jars on hand, giving 90 days of stock. Since 90 days of stock minus 70 days of lead time leaves only 20 days of buffer, the store needs to place the next order within 20 days to avoid running out.
Common mistakes
- Treating a 60-90 day lead time item the same as a local supplier that ships in 3 days.
- Forgetting that lead times for overseas suppliers can stretch further around holidays or peak shipping seasons.
- Not keeping enough safety stock to cover delays, since a stockout on a long lead time item can last months.
Long lead time items and SteadyShelf
SteadyShelf tracks each supplier's lead time separately and flags the order-by date for long lead time SKUs so they do not get missed next to faster-moving items.
SteadyShelf is launching on the Shopify App Store. Join early access to get the install link first.
Related terms
Lead time · Lead time variability · Safety stock · Reorder point · Supplier lead time variability
FAQ
How do I know if an item counts as long lead time?
There is no fixed cutoff. Compare the supplier's lead time to how fast the item sells. If the lead time is longer than your usual reorder cycle for other items, treat it as long lead time and plan further ahead.
Should I hold more safety stock for long lead time items?
Usually yes. The longer the wait for a reorder, the more can go wrong with demand or shipping delays, so extra safety stock reduces the risk of running out before the new order arrives.
Let SteadyShelf do this math for every SKU
Order-by dates per supplier, seasonal forecasts and draft POs for your Shopify store. $29/month after a 30-day free trial.
Get early access